Dublin GAA Centre Of Excellence
What’s included
Phase 1 of the project includes the following:
€8.5m – Main Contractor & PSCS
€3.1m – Pitch Works
€1.4m – Floodlighting
€850k – Spectator Stand
Breakdown
4 full-size, floodlit GAA pitches (grass & synthetic)
Renovated & extended clubhouse with changing rooms, offices, and meeting spaces
New indoor training facility, spectator stand for 500, and fitness areas
Walking/jogging trail, outdoor gym, speed training zones
PV panels, green roofs, and sustainable drainage.
When Will Works Begin?
Work is expected to begin Q1/2 of 2026 (March/April).
What’s Next?
Tyrrelstown GAA
Completion of phase 1 will allow for the next development stage, which would eventually see the completion of Tyrrelstown Gaa new grounds.